Snow load and wind load in Greenland — zone-specific design

Greenlandic construction projects are designed for zone-specific loads that are often 2–4 times higher than in Denmark. Here is how it is handled in CemPU projects.

In a nutshell

  • Snow load: Greenlandic projects are typically designed for 2.5–4.0 kN/m² vs. Denmark's 0.9–1.2 kN/m²
  • Wind load: Wind speeds up to 55+ m/s in exposed areas vs. 24–27 m/s in Denmark
  • Zone-specific: Roof and façade are dimensioned to local data — not a single Greenlandic baseline
  • EN 1991: The standard applies in Greenland too — only the values are higher
  • CemPU's capacity: Standard elements are dimensioned for arctic loads from production — project-specific documentation is delivered with drawings

How high are snow and wind loads in Greenland?

Snow load and wind load are two of the most project-defining design parameters in Greenlandic construction. Where a Danish construction is typically designed for a snow load around 0.9–1.2 kN/m² and a wind speed around 24–27 m/s, Greenlandic projects can be at 2.5–4.0 kN/m² snow load and wind speeds up to 55+ m/s in exposed areas.

These values cannot be ignored — they determine element thickness, anchoring, joints and spans.

What determines the snow load in a Greenlandic project?

Snow load is calculated per EN 1991-1-3 with project-specific parameters:

In Greenland it is entirely common to see design snow loads of 3.0 kN/m² and above for roofs and 2.5 kN/m² and above for wall load under particular conditions.

What determines the wind load in a Greenlandic project?

Wind load is calculated per EN 1991-1-4 with:

In particularly exposed areas (fjord mouths, high points), the design wind load can be 2–3 times higher than typical Danish values.

How are CemPU elements dimensioned for arctic loads?

CemPU consists of stiff sandwich elements that are themselves very strong — the solid cement facing gives high load-bearing capacity in both bending and shear. But the design is not only about the element itself, also about:

How does Tekment document load dimensioning per project?

For each Greenlandic project, Tekment prepares structural documentation that directly addresses BR2006:

This reduces the consultant's need for project-specific check calculation and accelerates the authority's processing.