Logistics to Greenland — container, season and installation window

The short building season imposes hard requirements on delivery sequence. This is how Tekment plans freight from Ringe to the site in Nuuk or a Greenlandic coastal town.

In a nutshell

  • Container efficiency: 100–150 m² wall per 40 ft sea container — typically twice that of imported prefab houses
  • Departure: From the factory in Ringe (Funen) to Aalborg or Aarhus port by haulier
  • Sea transport: Royal Arctic Line runs scheduled sailings to Nuuk — onward by coastal vessels to settlements
  • Unloading sequence: Containers are labelled with project ID and packed so elements come out in installation order
  • Sailing planning: 6–8 week lead time from order to site — critical to plan before the building season

How is CemPU transported from factory to port?

CemPU is produced at Tekment's factory in Ringe on Funen. Finished elements are packed on the Danish side with sea-transport packaging and delivered by haulier to the port of departure — typically Aalborg or Aarhus depending on the sailing schedule.

Packing is optimised for 40-foot sea containers: approximately 100–150 m² of wall per container, depending on element thickness and element height. Each container is marked with project identification and unloading sequence so that the elements come out of the container in the correct order during installation.

How does sea transport via Royal Arctic Line work?

The containers are shipped with Royal Arctic Line — the dedicated Greenlandic shipping company operating fixed routes between Aalborg/Aarhus and Greenlandic ports. Sailing frequency varies over the year; in the summer months there are weekly departures, in the winter months reduced frequency.

From Nuuk, Royal Arctic Line handles onward connection to coastal towns such as Sisimiut, Ilulissat, Aasiaat, Maniitsoq, Qaqortoq and Tasiilaq. Transit time varies between 7 and 21 days depending on destination and route.

How does the short building season affect logistics?

The effective installation season in most Greenlandic towns is May–September (4–5 months). Within that window the following must take place:

With traditional masonry or in-situ cast construction it is almost impossible to complete everything — mortar and concrete require +5 °C and drying time. With CemPU elements the building envelope can be installed in days without wet processes, freeing up time for the remaining building stages.

How is a Greenlandic construction project planned in practice?

To hit the installation window we typically plan backwards:

This means an installation in June-July requires project approval no later than February-March. Early dialogue is decisive for hitting the building season.

What must the Greenlandic site prepare before delivery?

Before the containers arrive, the site must have:

Need professional sparring on a Greenlandic project?

Send drawings and a short project description — we will assess relevance and documentation needs against BR2006.

Contact Tekment Greenland