In a nutshell
- Building season: May–September in most Greenlandic towns — 4–5 months in which the envelope must be closed
- On-site cast concrete: Requires +5 °C during pour and 28 days of curing — fits poorly in the short season without curing tents
- Prefab advantage: CemPU closes the shell in 5–11 days independent of temperature — frees the season for subsequent trades
- Capacity per season: With prefab one installation crane can complete 3–4 houses per summer vs. one house with on-site cast concrete
- Risk profile: On-site cast concrete risks overwintering with open constructions → moisture, frost, delays and cost overrun
How long is the effective building season in Greenland?
The effective installation season in most Greenlandic towns is May to September — that is, 4–5 months in which the temperature and weather permit meaningful outdoor construction work. Within that window the entire building envelope must be closed; otherwise the project risks running into winter with open constructions — with the associated moisture, frost and delay problems.
This is a completely different time horizon from Denmark, where the building season is in reality the whole year. That difference changes which building methods are even realistic.
How long does in-situ cast construction take in Greenland?
A 200 m² residential building with traditional masonry or in-situ cast construction typically requires:
- Foundation cast and cured: 2–3 weeks
- Wall masonry or casting: 4–8 weeks (depending on crew and weather)
- Drying time and tightness tests: 2–4 weeks
- Roof build-up: 2–3 weeks
- Closure of building envelope: a further 1–2 weeks
Total: 11–20 weeks, often at the higher end due to weather dependence.
In a 4–5 month window there is not much room for delay. One week of precipitation early in the season can push closure into October — which is borderline winter.
How long does prefab CemPU take in Greenland?
The same 200 m² residential building with CemPU:
- Foundation cast and cured: 2–3 weeks
- Container delivered and unloaded: 1–2 days
- Element installation (building envelope): 1–2 weeks
- Roof build-up: 1–2 weeks
- Closure of building envelope: part of installation
Total: 4–7 weeks, primarily depending on crane logistics and crew — not the weather.
The difference frees up 4–13 weeks for internal works, fit-out and quality assurance before winter.
How many craftsmen do the two systems require?
Traditional in-situ cast construction requires multiple trades on site simultaneously:
- Bricklayers
- Concrete workers
- Insulators
- Carpenters
- Auxiliary crew
In Greenland, every trade has to be flown in, accommodated and paid. Personnel logistics is often a greater challenge than material logistics.
CemPU installation is handled by a small qualified team (3–5 people plus a crane operator). The entire building envelope is one trade that is trained on a single delivery.
What economic risks do in-situ cast vs. prefab carry?
In a tight building season, time risk is often the largest economic item — not the material price. Delay means:
- Extended accommodation costs for personnel
- Re-mobilisation the following summer (transport, accommodation, start-up)
- Risk of moisture and frost damage on open constructions
- Delayed building use (rental income, occupation)
Prefab markedly reduces this risk because the process is predictable: container arrives on date X, installation team arrives on date Y, building envelope is closed on date Z. The weather can still play tricks, but the intervention window is short enough that the weather forecast is reliable.
When does in-situ cast concrete still make sense in Greenland?
In-situ cast and masonry construction still has its place in Greenland — particularly:
- Small buildings and outbuildings where logistics is simpler than freight
- Renovation projects on existing foundations
- Buildings that have to match a very specific local architectural tradition
For new construction of real size — housing, institutions, commercial, industrial halls — prefab is typically the only realistic way to close the building envelope within a single season.