From drawing to weathertight shell in 5 days

A typical detached house reaches a weathertight shell in ~5 days with CemPU. We show the day-by-day schedule so you can see what is required from your side and what we deliver.

From drawing to weathertight shell in 5 days
5 days
typical detached house
Weathertight shell
from foundation
CNC
±1 mm
Precision
from production
0 L
construction moisture
No drying time
trades can continue
Mobile crane
entire installation
Logistics
one delivery

The 5 days in detail

Day 1 – Foundation ready

By the time CemPU arrives, the foundation should be cast, levelled and ready. We provide a foundation specification tailored to your project.

Day 2 – Wall panels lifted

Panels are delivered CNC-pre-machined and lifted into place with a mobile crane. Typically 8–12 wall panels in a day.

Day 3 – Roof and joints

Roof panels (SIPS Roof 336) are installed. Joints are sealed with FR acrylic and foamed with Graft FR.

Day 4 – Windows and openings

Windows and doors are installed in the CNC-cut openings. No on-site adjustment.

Day 5 – Closed, dry, ready

The envelope is closed. Internal trades can start without waiting time. No construction moisture to drive out.

Sources and documentation

Get a schedule for your project

Send the drawing and we will deliver a day-by-day installation plan.